The Philippine Senate has committed to removing 295 infrastructure projects worth ₱8.836 billion from the proposed 2027 national budget after the Department of Public Works and Highways (DPWH) identified deficiencies in their supporting documentation.
The announcement, made by Senate President Sherwin Gatchalian on November 3, follows an earlier commitment by former Public Works Secretary Vince Dizon to prevent infrastructure projects from entering the budget without complete technical requirements.
The decision marks a concrete step in enforcing the government’s new screening rules. However, the proposed cuts remain subject to the continuing budget process, and the final allocation of funds has yet to be established.
The commitment made in August
On August 26, Dizon told the House Committee on Appropriations that the DPWH had introduced stricter procedures for evaluating infrastructure projects proposed for government funding.
Under the revised system, projects must satisfy five documentary requirements: an approved program of work, validated geotagged photographs, compliance with Budget Preparation 202 requirements, a Certificate of Implementability, and an appropriate master plan, feasibility study or equivalent local authorization.
Dizon explained that projects would be selected according to demonstrated needs rather than the previous allocation formula. He also said projects missing the required documentation could not be included in the budget.
The department initially proposed reducing its infrastructure project list to approximately 11,395 for 2027, compared with more than 25,000 projects annually in 2024 and 2025.
The reductions were intended to address duplicate and overlapping projects and prioritize infrastructure considered ready for implementation.
How the Senate identified the projects
The Senate’s examination of the proposed budget revealed significant differences between the executive branch’s original spending plan and the version approved by the House of Representatives.
According to Senate finance committee chairman JV Ejercito, the number of DPWH projects increased from approximately 11,420 in the original National Expenditure Program to 16,244 in the House-approved General Appropriations Bill.
During an October 26 consultation, Ejercito reported that supporting documents had been submitted to the Senate committee for only 1,418 projects. Documentation for another 14,826 projects had not been submitted at the time of the review.
The committee flagged approximately ₱266 billion in infrastructure projects for further examination.
The absence of documents submitted to the committee did not automatically establish that the projects were fraudulent or that the necessary records did not exist.
Separately, Gatchalian said a review of 11,395 projects had identified 7,107 with at least one budgetary warning sign. These included missing geographic coordinates, overlapping projects, fragmented allocations and inconsistent descriptions of proposed work.
Following further evaluation by the DPWH, Dizon reported that 295 projects, collectively valued at ₱8.836 billion, failed to meet the department’s requirements.
What changed in November
On November 3, Gatchalian announced that the Senate would remove the 295 projects from the proposed 2027 budget.
He stated that infrastructure allocations lacking verifiable technical support would receive no public funding.
The following day, the DPWH publicly supported the move. Newly appointed Public Works Secretary Giovanni Lopez confirmed that the department would continue applying the documentary requirements introduced under Dizon.
Lopez also attributed the stricter approach to President Ferdinand Marcos Jr.’s directive that projects lacking proper documentation should not proceed.
The department’s position extends beyond budget preparation. Lopez said projects without the necessary documentation should not receive funding or proceed to implementation, even if they had been included through congressional amendments.
What remains to be verified
The latest announcements establish that the DPWH identified 295 noncompliant projects and that Senate leaders committed to removing their proposed allocations.
They do not establish that all the projects flagged during the wider Senate review have been rejected. Nor do they demonstrate that the documentation requirements have been consistently applied to every infrastructure item in the revised budget.
The final assessment depends on whether the 295 projects remain excluded from the approved 2027 budget, whether additional projects are removed following verification and whether any previously rejected allocations are restored after documentation is submitted.
The procedure however is still in progress. The screening process has produced identifiable findings and a Senate commitment to remove ₱8.836 billion in proposed projects. Final budget approval and implementation remain outstanding.